Flagship Renovation Without Losing a Single Day of Sales
Oversaw the largest renovation in the history of the world’s largest store, adding 15,000+ sq ft of selling space, managing complex structural work, and repairing strained internal relationships to bring the project back on track.
$5M+ Annual Savings Through Snow Operations Overhaul
Analyzed performance gaps for a major U.S. bank and redesigned the entire snow removal ecosystem—improving communication, validating service levels, and eliminating unnecessary spend.
Stabilizing 100+ Unsafe Display Units Across Two Countries
Rapid response strategy, temporary stabilization plan, custom retrofit package, and coordinated installation—all completed within six months.
Engagement Models
Fractional VP of Facilities, Interim Construction Program Lead, Portfolio Audit + Improvement Roadmap, FM Program Development & Buildout, Construction PMO for Rollouts & Remodels, Vendor Strategy & RFP Leadership, Ongoing Executive Advisory